We are ahead of schedule at our Baydo Pointe project, but are working long hours to beat the coming cold weather. Hopefully it can stay above freezing for a couple more weeks!

Our speed is thanks in large part to the use of Doka-supplied panel formwork. Every time I use the system I am impressed with it’s speed and versatility. We are currently pouring 150′ of wall every week, and I feel like we could go faster if we had more forms on site. And we don’t require a lot of manpower — a crew of 3-4 workers can strip out and stand (one-side) the formwork in 2 days, and button up in another day.

The structural concrete at this 6-story apartment building is confined to the parkade perimeter walls and footings. The floors and walls are pre-cast concrete mounted on steel columns and beams. It will be interesting to compare the pace of construction of this project to the adjacent wood-frame apartments, which are also 6-story.

The very first section of parkade walls – September 20th pour date
Setting up the concrete pump for a morning pour November 1st.
Completed parkade walls.
A stand-alone section of Doka wall formwork.

 

Two Edmonton Grocery Stores

Tundra recently completed the foundations for two new Edmonton grocery stores: a Co-op Food Store located in the Orchards neighbourhood, and a new Sobey’s FreshCo located on Manning Drive. We’re proud of our workers for completing both jobs on extremely tight schedules, and it was great to work for these two general contactors again: Norson Construction and Eton-West Construction!

 

Mina Harvey

Engineer

Erik Chandler

Support Staff

 

FCL/Co-op Lumber Distribution Hub is out of the ground!

 

 

 

We love hearing how easy it is to build on our foundations! Tundra completed the grade beam for the new FCL/Co-op Lumber Distribution Hub in Fort Saskatchewan, AB with 100% accuracy on our anchor bolts. The steel erecting crew was able to place the building with zero problems!

For anyone who doesn’t know structural concrete, these high-strength anchor bolts cast into the concrete play a vital role: they transfer the loads from the steel column to the foundation. Their location needs to be extremely accurate, typically within 3 or 6mm!

We’re proud that we got it done in the middle of winter, with temperatures dropping as low as -25C. We were able to maintain our schedule despite the extra time needed to heat the formwork, rebar, and concrete while it cured.

Thanks to our client, Pemco Construction Ltd. and site superintendent Jordan Woods – you were great to work with! Looking forward to the next one!

 

 

St Thomas Aquinas School

Provost, AB

We are proud of the work we completed for Jen-Col Construction! The new St Thomas Aquinas School project was a great experience and the team at Jen-Col was responsive and easy to work for.

The project itself was fairly standard: 5’ foundation wall on footing throughout. The only out-of-the-ordinary concrete formwork were the two suspended concrete beams above large gymnasium openings.

Our scope was completed in early October 2020.

t Th